When you use Control Chart Builder with a process variable that has a spec limit property, JMP will also show the capability analysis (very nice). When you add a Phase variable to the control chart, the process capability goes away which is disappointing, and the option to turn on the Process Capability analysis goes away as well from the LRT. So my questions are:
1. Why does the Capability analysis disappear when a Phase variable is added (ie. is there some mathematical justification)?
2. If a phase variable is added, wouldn't it make sense to split the capability analysis by that phase variable rather than disappear it?
This question comes up a lot from our customers and I don't have a good answer for it, so hopefully someone here knows.
Thanks,
Mark