Hi all,
I didn't find a particular topic that addressed this so I was hoping to get some help from some of you folks that use RSS.
Basically there's two things I'm trying to do in the simulation engine to account for real-life response for maintenance cycles:
1) If I have two parallel components, both of which have failures and scheduled items, I would like to be able to suspend the scheduled item for the parallel component when it's parallel block is failed. This is to model normal response in production facilities where maintenance would be deferred to prevent the loss of a system.
2) Is there a way to stagger maintenance schedules so they don't overlap if they're still on the same schedule (i.e. they get completed annually, but staggered 3 months apart from each other).
I imagine that using an If block might be applicable for this but there's not any real documentation for me to reference to figure out its use.