Hello everyone,
I'm a novice JMP user and thanks in advance to any advice you can give!
I'm interested in the main effects and two way interactions for four, continuous, 2 level factors in my process. Using the Custom Design to create my DOE, I get a minimum of 11 runs. Each run will likely take a couple of hours for the process to settle out after a change. If I assume my current process operates at the center points (this may or may not be a good assumption), I can add 3 center points runs with minimal impact to the overall experiment time. A center point run going into and out of the experiment, and one somewhere during the experiment. Does this sound okay?
Is there a more efficient design to understand the main effects and two way interactions?
Thanks.