Hi JMP Community,
I have a response variable that goes from 0 to 100% and following a quadratic function in response to a continuous variable. The vertex of which can only go up to 100%. The problem I'm having is that there's a nominal factor that can shift this function to the left and to the right. So far, I've filtered for responses to less than 80% to make the regression mostly linear (2nd order coefficients not having an effect) such that the nominal factor can be added to the fit model. I get estimates of the nominal factor that shift the quadratic function up and down but really the quadratic function is shifting to the left and to the right due to the nominal factor. How can I model this relationship in JMP?
I'm assuming my model looks something like this y_hat = (x-b_0)^2*b_1+(x-b_2)*b_3+b_4+error where b are regression estimates.

Figure 1: Toy example of the situation. Where the blue line is the response to one level of the nominal factor. The red line is another response to a different level of the nominal factor.