Hi;
Is there any way to have JMP calculate a formula in working days like the WORKDAY function Excel? I.E. 3/22/2019 + 1 day would be 3/25/2019 and not 3/23/2019.
Thanks!
This function will do the trick. Takes two arguments: a date and the number of days to add (or subtract if negative)
workday = function({one_date, add_days}, {local new_date, dow}, new_date = date increment(one_date, "Day", add_days); dow = day of week(new_date); if (dow == 7, // Saturday new_date = date increment(new_date, "Day", 2); , dow == 1, // Sunday new_date = date increment(new_date, "Day", 1); ); new_date; ); testdate = informat("3/22/2019", "m/d/y"); workday(testdate, 2);
Output from the log:
25Mar2019