Definitive screening design blockingHi All,
I have some colleagues that are considering running a definitive screening design for a pilot plant production scale run, and have asked for my help in creating a DOE for them.
The pilot plant runs on a day/night shift fashion. What I'm curious about is if it's possible to get JMP to for the output DOE table to alternate runs in a day/night fashion. I can block or add a categorical factor in there to represent the day/night shifts, but I can't get JMP to force the output table to alternate based on that column. I can always do it manually with a script or via a column formula, but wondering if there is already some built-in method to do this.
Thanks!,
DS
Re: Definitive screening design blockingWhat version of JMP are you using?
You could create an indicator column separate from the design and use a sort to achieve the order that you want.
I used JMP 14 and the blocking option in DSD platform. I created a DSD for 5 continuous factors. (I know, not really a screening situation.) Here is the result without blocking:

Then I decided to create 4 blocks for 2 shifts over 2 days. I want to be able to estimate the potential quadratic terms. Here is the result:

Here it is the same design with the Randomize within Blocks option selected:

Is this example not what you are trying to do?